Earned value management (EVM) techniques promise to give project managers a powerful early warning system for programs veering dangerously off course. But like committing to an early morning calisthenics routine or starting a low-carb diet, adopting EVM is sure to cause some initial pain.
Regarded as a solid means of forcing discipline on project teams and contractors, EVM provides a method for program officials early on to determine if a project will be successful — whether it will come in on budget and on schedule or abysmally miss both marks. What follows is a list of frequently asked questions and explanations gleaned from EVM experts, who described this method of project management and its use in government.
What is EVM?
With Defense Department roots dating to the 1960s and widespread use in the aerospace industry, EVM is a rigorous cost-containment strategy now undergoing a bit of a renaissance in federal information technology contracting. Specifically, Office of Management and Budget officials, in a drive to impose cross-agency performance measures, are demanding that program managers show proof that they have technology programs under control. EVM is a way to give OMB the wealth of budgetary feedback now required, experts say.
For instance, OMB directives spurred the Pension Benefit Guaranty Corp. (PBGC) to use EVM techniques for more than 100 projects, said Valerie Sandy, PBGC's project office administrator. "Most of our earned value calculations are driven by OMB, which is the agency that provides funding for our initiatives," she said. "Risky cost-based, rapid-response contracts involving complex technology are also forcing government to embrace earned value as the most effective tool for managing such contracts."
How does EVM work?
Basically, EVM involves breaking down an IT project into manageable chunks at the project's inception and then clearly delineating individual work tasks and affixing budget figures to each of those measurable work packages. At prescribed points during the project, officials will do more than simply compare how much an agency has spent on the project against how much was earmarked for expenditure — the basic steps that make up traditional planned vs. actual expense methods.
Instead, project managers using EVM will take the amount spent on a particular task during the time frame and tie it to the amount of work a contractor has accomplished. Then, officials will compare those figures with what program managers had planned to spend and the work contractors had promised to finish. Comparing those numbers yields earned value.
How would EVM work in a government IT setting?
To get a feel for EVM in action, consider this example offered by Quentin Fleming, an author of books about EVM and senior consultant at Primavera Systems: Suppose there is a 12-month, $1 million software project with 10 deliverables, each of which is budgeted at $100,000. At the end of the first quarter, assume the project team in charge has spent $300,000.
In a traditional planned vs. actual analysis, the project would seem to be on target. But what if the vendor had completed only two of the 10 tasks instead of three as prescribed at the project's onset? This means that $300,000 in funds was spent to accomplish $200,000 worth of work. It soon becomes obvious that this project's future, which appeared so bright at first, is now "not so good when we realize that for each dollar we spent, we got only 67 cents of value earned," Fleming said.
Although planned vs. actual analysis is standard operating procedure for most contracts, it is a practice that often lacks accountability measures, said Wayne Abba, an independent EVM consultant who used the techniques extensively in his earlier DOD career. "By just showing expenditures, you have no idea how much work has actually been performed," he said.
What are the major benefits of EVM?
More than anything, EVM is a method of imposing new levels of accountability on a project and shining a light on potential problems while there is still time to fix them, said Gary Humphreys, another former DOD official who has used EVM extensively. He is now chief executive officer of Humphreys & Associates. "This sets up an early warning system for the program," he said. "Basically, it forces you to do your homework upfront."
Further, EVM gives program managers a way to anticipate and cope with the unexpected expenditures and events that plague many projects. "One of the big things possible with EVM is management by exception," said Ruthanne Schulte, EVM software product manager at Welcom, which develops project portfolio management software. "Cost variances can be highlighted in red, for example, and officials can investigate these areas before they run out of budget."
Will government agencies buy into EVM?
Experts appear split on the technique's future in government, with no consensus on whether a significant migration to EVM will take place. "EVM is still not widely accepted in the agencies," said Schulte, who expects that OMB management processes will push more agencies toward EVM. "New contracts will require EVM in order for the agency to receive high scoring to get all of their projects funded," she said.
Others aren't so sure. "Despite its benefits as a management tool, use of EVM will not increase significantly in the next few years," said Ray Bjorklund, senior vice president and chief knowledge officer at Federal Sources.
Bjorklund said EVM will remain strong at DOD, NASA and other agencies that build complex systems. "But there are fewer and fewer IT contracts of the scale that would warrant EVM," he added. "Similarly, there are far more fixed-price type contracts than the cost type contracts where EVM may be used."
Still, opportunities to use EVM exist. For instance, officials at U.S. Customs and Border Protection's Modernization Office incorporated EVM into the Automated Commercial Environment program, said Dave Morrell, the office's team leader for project management. "EVM is employed on cost-reimbursement task orders only," he said.
Morrell predicts wider adoption of EVM among government IT program managers. "A broader understanding of EVM and its benefits within the IT industry will further expand its use throughout the federal government," he said. "EVM is a substantial improvement over the subjective indicators often used in projects reporting past performance, and [the strategies] provide the project manager with more reliable tools with which to predict future performance."
How difficult is it to incorporate EVM into projects?
Beyond the initial challenges in setting up an EVM system, which still requires a good deal of planning, project managers should prepare for the negative reception the new methods are likely to get from staff members and contracting teams. EVM is almost always a tough sell, and all involved are likely to balk at the level of discipline they will face once the technique is enforced, experts say. "Yes, there is going to be some resistance," Fleming said. "Some project teams will fight it."
Much of this reluctance will be tied to the tendency to avoid more disciplined work processes, but other factors could be in play, Schulte said. "I've seen some of the biggest problems with people who know they are in trouble and don't want to open the kimono," she said, adding that some contractors may fall into this category.
How can managers encourage staff to buy into EVM mandates?
To get past initial EVM resistance, program managers can walk teams through the many reasons why EVM will bolster a project's performance. Coaxing has its limits, however, so officials likely will have to drive home the fact that using EVM is not optional. It then becomes a matter of giving staff members time to adjust to the new level of discipline, experts agree.
PBGC executive managers and stakeholders began requiring standardized, EVM-compliant monthly reports to get past resistance to the new processes. "This is how we overcame the human factor of any potential noncompliance," Sandy said. "Users did not want to have reports generated from nonstandard project plans." With personnel quickly onboard, agency officials were able to accomplish a series of goals. "Project planning is standard, resource leveling is realistic, and all tasks are capturing actual hours worked," she said.
What potential pitfalls come with EVM?
Failure to properly define a project's scope and map tasks as they relate to the larger context are the quickest ways to sabotage EVM. Program managers must study all aspects of a project before work is dissected into measurable tasks. "You have to define the scope of project you are working on in order to measure the percentage of work completed," Fleming said.
It is also important not to get carried away, micromanaging every detail of a project and figuring costs down to the penny. "Resist overkill," Humphreys said. "If you can measure the status of a project at the milestone level, don't go to the 'yardstone' level. If you can do it at the 'yardstone' level, don't go to the 'footstone.'" Managers also must be careful not to apply EVM too broadly. "It may not be right for every project," Abba said. "See how a particular program fits in a portfolio of projects that are related." Sometimes a particular effort should be given a more flexible budget, he added.
Once program officials have decided where best to apply EVM and have come up with sound baseline plans and reasonable measurements for assigned tasks, it is crucial to make expectations clear to all involved. "Make target costs open and visible," Abba said. "Let people know exactly what they will be accountable for."
Home
»
Resources
»
Earned Value Management
»
Vital Checks for Better Health: How Earned Value Management Can Keep Your IT Projects on Track
04 Saturday, Feb 2012
Categories
-
Editing (2)
-
Graphics (4)
-
Marketing (8)
- How To Take Advantage of Proposal Lessons Learned
- How to Increase your Win Ratio in One Easy Step
- Court wrestles with “commercial item” definition
- Market Intelligence as a Competitive Edge
- Relationships: The Core Concept in Building Government Business
- When Hunting for Contracts, Never use a Shotgun
- How Can a Small Business Win More Contracts?
- Marketing Positions Small Business to Win
-
Key Personnel (3)
-
Red Team (5)
-
Proposal Writing (19)
- A Current Look at the Proposal Market
- Volume of Proposal Activity in the Fall
- Should You Write The Executive Summary First or Last
- A Whole New Way to Think About Sales Proposals
- Fog Index and Pace
- Strategy-Theme-Discriminator Tree Development
- Write a Winning Transition Plan
- Proposal Strategy Tree
- Effect of the Stimulus on Government Contracting and Proposal Activity
- Keep Your Sentences Short: Why Shorter Is Better
- Eliminating Background Noise
- Avoiding Death by Bullet Point
- Leading Non-Professional Proposal Writers
- How to Write a Better Proposal Introduction
- Writing Persuasive Reasons Why Customers Should Select You
- When to Start Writing Before the Final Solicitation
- Resumes - Hints on Preparing Winning Resumes
- Management Plans: What Makes a Quality Management Plan
- Tell 'em, and tell 'em, and tell 'em again
-
Resume Preparation (2)
-
Proposal Coordination (3)
-
Writing Past Performance (3)
-
Orals Coaching (18)
- How to Select an Orals Coach
- Can’t We All Just Get Along?
- Ten Tips for Presenting to Senior Executives
- Bring Home the Bacon! Part Two:
- Bring Home the Bacon! Part One: Why Project Managers Should Improve Their Presentation Skills
- How “Beetle Bailey” Can Improve Your Presentation Skills
- Why Oral Presentations are Important: Part Two - The Murder Board
- Why Oral Presentations are Important: Part One
- How to Increase the Economic Impact of Your Presentations
- 7 Uncommon Power Point Techniques
- Business Developers: How to “Fix” Your Presentations
- Benefits of an Effective Orals Strategy
- Videotaped Oral Presentations
- Hey Coach! Help Me With Rehearsals!
- How to Select an Orals Coach
- Orals Coaching - "It's All in The Attitude!"
- Orals - Hey Coach! Help Me With My Body Language
- Orals - Knowing the Room Improves the Presentation
-
Proposal Protests (5)
-
Proposal Management (25)
- The Proposal Plan: The Proposal Manager Prepares this Document to Guide the Proposal Creation Activity
- Analyzing the Final Solicitation
- Getting Prepared to Win Large Proposals
- Difficulties in Determining Best Value
- The Proposal Manager's Tasks
- Maintaining Positive Contracting Officer Relationships...A List of Do and Don't Recommendations
- Unsolvable Problem: Your Proposal Team Argues over Proposal Quality
- Planning Your Solution vs. Planning Your Content
- The Proposal Plan: The Proposal Manager Prepares this Document to Guide the Proposal Creation Activity
- Five Popular Ways to Write A Losing Proposal
- Cost of Preparing Proposals
- The Challenge of Preparing Task Order Proposals
- Why Create Your Own Draft RFP?
- Asking Questions on Your Next RFP
- Five Easy Ways to Improve Your Proposals
- Proposal Departments: Whether to Use Permanent Staff or Consultants
- Volume Management: Getting the Best, Quickly, from Your Subject Matter Experts (SMEs)
- The Proposal Plan: The Proposal Manager Prepares this Document to Guide the Proposal Creation Activity
- Tips on Winning Proposals
- Pre-Proposal Goals Help Build Winners
- Storyboards Why Bother?
- The Top 10 Ways to Lose a Proposal
- The Top 10 Ways to Ensure Proposal Success
- The First Five Days
- Decomposing a Solicitation can be Fun
-
Miscellaneous (12)
- 2011 Highlights and Board Meeting
- OCI Supporting Innovative AIDS Research Program
- When pre-bid Q&A raises more questions than answers
- Will the Appropriations Bill Ever be Approved?
- Customs and Border Protection (CBP) to hire 1,000 IT workers during fiscal 2011
- Defense Appropriations Act Prohibits Mandatory Arbitration
- House Passes Defense Bill That Would Reduce Use of Contractors
- PRESIDENTIAL MEMORANDUM ON GOVERNMENT CONTRACTING - RESERVING WORK FOR FEDERAL EMPLOYEES
- OMB Memorandum 10-26 Immediate Review of Financial Systems IT Projects
- President Obama's Affect on Proposal Work
- Ten Practical Rules For Protecting Rights In Technical Data And Computer Software
- Elements of a Good Product Demonstration
-
Earned Value Management (1)
-
Competition Analysis (8)
- Win Strategy General Guidelines — Strategy Definition and Planning
- Win Strategy General Guidelines — The Self Analysis
- Win Strategy General Guidelines - The Competitor Analysis
- The Proposal Manager's Four Uses of Competition Analysis
- Win Strategy General Guidelines - The Customer Analysis
- Competitive Analysis Considerations
- Win Strategy General Guidelines - Competition Data Base Requirements and Approach and the Opportunity Analysis
- Developing Competitive Intelligence on Service Contracts
-
Risk Management (1)
-
Capture Management (19)
- The Business Capture Report Card - Phase Five
- The Business Capture Report Card - Phase Four
- The Business Capture Report Card - Phase Three
- The Business Capture Report Card - Phase Two
- The Business Capture Report Card – Phase One
- The Business Capture Report Card - Introduction
- How to Capture the Win
- Proposal Writing Myths and Realities
- Proposal Espionage, a Cautionary Tale
- Why Should the Customer Select You?
- The Art of not being eliminated
- What Makes a Must Win Opportunity Any Different?
- 47 Things to Know Before The RFP is Released
- Alternate Proposals Why You Should (Almost!) Never Submit One
- Program Manager: To Win, You MUST Offer a PM with Customer Recognition
- Ten Things You Probably Did Wrong on Your Last (Losing) Proposal
- Capture Plans: To Win the Proposal Manager Must Bring These Elements into the Proposal
- The Different Customer Roles in Vendor Selection
- What's the Most Important Thing to Know about Winning Proposals?
-
Proposal Evaluation (1)
-
Government Procurement (7)
-
Proposal Group Management (11)
- Proposal Departments: Whether to Use Permanent Staff or Consultants
- 7 Principals That Should Guide Your Proposal Process
- Proposal Departments: Whether to Use Permanent Staff or Consultants
- Do You Have a Proposal Process, or Just Think You Do?
- Who Should Write The Proposal
- How To Get A Proposal Software Purchase Approved
- Building a Proposal Development Capability
- 7 Principals That Should Guide Your Proposal Process
- Creating and Managing Boilerplate
- How Do Your Proposal Processes Compare with "Best Practices"?
- Developing a Proposal Library
-
Contract Management (9)
- "Incumbent-itis”: How Incumbents can Lose the Proposal Competition
- Defending Incumbent Contracts - The "Vulnerability Assessment"
- Why Your Company Should Consider the Blanket Purchase Agreement
- Pricing Adjustments
- Wired RFPs
- Inexperienced Negotiators
- Sole Source - The Voice of Experience
- Post Award Debriefs
- Do Contractors Have to Police the Government?
-
Business Development (8)
- The Proposal Market in 2012
- Predictions for the Proposal Market in FY 2012
- Business Development Goals Creating Winning Teams
- The Goal of Good Business Development
- The Role of the Pipeline in Managing Business Development
- 101 Things Your Business Development Process Should Address
- Managing the Transition from Business Development to Proposal
- Simple Guidelines Small Business can Use to Measure Business Development
-
Virtual Proposal Preparation (1)
-
Unsolicited Proposals (1)
-
Performance Based Service Contracts (PBSC) (3)
-
Grants (1)
-
Executive Summary (1)
-
First Time Proposals (2)
-
Training/Education (2)
- Expand All
- Collapse All
If you enjoyed these articles and would like to receive our monthly newsletter.
Key Concepts
- Government Proposal Writing
- Proposal Training
- Win Government Proposals
- Government Proposals
- Federal Proposals
- Federal Proposal Writing
- Writing Government Proposals
- Win Government Contracts
- Government Proposal Capture
- Government Proposal Management
- Government Proposal Manager
- Orals Coach
- Government Proposal Coordinator
- Government Proposal Technical Writer
- Government Proposal Volume Lead
- Proposal Volume Lead
- Resume/Past Performance Writer
| About OCI | Contact Us | In House Proposal Facility | OCI Newsletter | User Agreement | Public Workshops | Follow us on Twitter | Site Map | Training | Survey |
Copyright© 2011 by Organizational Communications, Inc.